- Slug: BC-CNS-Light Rail Extension,1000
- Photos available (thumbnails, captions below)
EDS: A previous version of this story included an error involving the cost of the light rail project. The revised cost is $965 million. The story also has gone through a significant rewrite to clarify the details of the council vote. Clients who used earlier versions are asked to replace the story and run the correction that can be found here.
By NICK SERPA and JESSICA ALVARADO GAMEZ
Cronkite News
PHOENIX – The Phoenix City Council on Wednesday agreed to proceed with the development of the South Central light-rail extension, however, the council also approved a motion directing Valley Metro to evaluate the possibility of maintaining four lanes of surface roads along portions of the $965 million project.
The number of lanes is a major sticking point with some residents and business owners.
Newly appointed Mayor Thelda Williams said the extension is a good project, and it will give people the “opportunity to be employed downtown.”
Councilman Daniel Valenzuela said stopping the project would have financial consequences.
“There is the potential the city risks losing hundreds of millions of dollars in federal money,” he said in a statement after the vote. “However, I feel confident that staff and Valley Metro will make an honest attempt to listen to residents to try and resolve their concerns while keeping the project on track to meet important deadlines.”
A grassroots community group had asked the council to delay the project by 90 days, and Williams had agreed to hear from residents. During an hours-long public hearing Tuesday, people packed the council chambers, but the council did not vote on the issue. Some residents spoke in support of the extension and many questioned the city’s transparency and the design of the 6-mile project, which is scheduled to begin late next year.
Much of the public response at Tuesday’s hearing focused on the plans to reduce traffic along Central Avenue to two lanes from four.
“We were not told any details … of the two lanes,” said Jimmy Cluff of South Phoenix. “We weren’t at those meetings because we didn’t know about them.”
In response, when the council met Wednesday to vote on the issue, Councilman Michael Nowakowski introduced a motion that would require Valley Metro evaluate whether the project could accommodate four lanes if it fits within the project’s “federally approved environmental footprint,” said Corinne Holliday of Valley Metro.
The council approved that motion 6-2.
Valley Metro now will examine whether it can do such things as remove bike lanes and vegetation to allow more lanes. The agency also will review alternative designs and conduct community outreach about the planned extension during the next three months, city spokesman Lars Jacoby said via email.
“It’s confusing because the business group asked for a 90-day pause, but that’s not what this is, it’s just a three-month period to do all that council asked – design review and outreach,” he said.
Councilwoman Kate Gallego and Vice Mayor Jim Waring voted “no” on the motion to explore extra lanes. Gallego, who has supported the extension, said Wednesday’s vote could threaten the project.
“I am deeply disappointed in yesterday’s vote, which jeopardizes a much-needed investment in the community I represent,” Gallego said in a statement released Thursday. “Valley Metro is under strict timelines and should focus their resources on our application for federal funding. Nearly $600 million of federal investment in our community is at stake – dollars that will be given to other states if we squander this opportunity.”
At Tuesday’s meeting, Phoenix and Valley Metro officials had defended their public-outreach efforts and warned that any delay could jeopardize federal grant money helping to pay for the project.
Deputy City Manager Mario Paniagua said the project faces a July 31 deadline to apply for the “federal engineering phase” of the project and planners would have to “start all over” if they miss that deadline.
Valley Metro CEO Scott Smith had said Valley Metro held more than 380 community meetings in South Phoenix regarding the extension, which will stretch from downtown to Baseline Road. He said meetings with affected business owners have taken place “well in advance of construction.”
At Tuesday’s meeting, Smith also noted that Proposition 104, the sales-tax increase to pay for the extension and other Phoenix transportation projects, was approved by 55 percent of voters in August 2015; the approval was 75 percent of voters along South Central Avenue, he said.
Nowakowski criticized Valley Metro’s efforts to educate and listen to the public: “We haven’t done our homework.”
In response, Smith said: “Part of those 380 meetings that were held over the last three years were with specific businesses.”
Nowakowski said many of the meetings were poorly attended, and many community voices might not have been heard.
Smith refuted this, saying Valley Metro hung about 20,000 door hangers related to the extension, and more than 150 people showed up for some meetings. He said Valley Metro had provided opportunities for community input and met federal requirements for public outreach.
“Unless you knock,” Waring said, “nobody cares about the door hangers.”
“If the council wanted to get rid of the South Central light rail,” he said, “we can’t do it unilaterally. But we have time to send something to the ballot.”
Celia Contreras, who owns Tony’s Window Tinting on Central Avenue and the founder of community group 4 Lanes or No Train, said Valley Metro officials still have not met with her as promised to discuss ways to help her business during construction. “We receive so many excuses.”
She said light rail could improve south-central Phoenix, but not with the current design, which she contends would cause traffic issues and negatively affect businesses along the line.
“We’re not against the light rail. We’re against the design of the light rail.”
Contreras also said she doesn’t believe voters were properly informed. Several of the conversations about the plans were held at festivals and events where it’s difficult to have meaningful, in-depth conversations.
“You have to listen, because you never want to listen to us,” she told Valley Metro and the City Council on Tuesday.
James Neal, co-owner of the Food City at Jesse Owens Boulevard and Central Avenue, said that although residents voted for Prop. 104, there wasn’t language indicating lane reduction on a “major arterial” road.
“One lane is not going to spur development,” he said, adding that roads are just as important as public transportation.
Victor Vidales, a father of five and a South Phoenix native, also supports the light rail, but he wants the city to create a neighborhood improvement plan to fix streets and sidewalks in the area.
“We need transportation options to connect our people to each other,” he said. “Phoenix has been designing communities around the car for way too long. Healthy communities are designed around people, not cars.
“I trust we can work together to survive the four-year period of construction. Many of us have waited a very long time to receive an equitable investment of this magnitude in our community.”
William “Sparky” Smith, a member of the Phoenix Citizens Transportation Commission, said he changed his mind about the extension after hearing about the lack of transparency.
“We’re not addressing the 800-pound gorilla in the room, and that is that elections have consequences,” he said.
For more stories from Cronkite News, visit cronkitenews.azpbs.org.
^__=